Clubhouse Update
We are optimistic that the interior of the Clubhouse will be complete by the end of March. Work pending as of the end of February includes final cabinet installation, wood staining, countertop installation, fireplace stonework and finally, carpet. All work is in process and scheduled and the Clubhouse interior is really coming together nicely. Come on down and take a look at the progress, play some pickleball or tennis and take a swim.
In the last few months, we have focused on completing the interior so our Members can begin enjoying the benefits of the new interior. Work is scheduled to commence on the exterior of the building and the parking lot on March 9th. We will send further scheduling updates via our This Week in Nellie Gail Ranch e-mails.